April 27, 2021

March Month in Review

The Month of March brought great weather and enabled both Apple Valley and Summitview to ramp up Civil, Site and Landscaping production – including the Community Walking Paths. Chervenell continues to manage and keep both projects on schedule. They have consistently worked to improve both project completion dates and subcontractor manpower – with above average totals. April will bring completion of curbing and parking lot asphalt. Remaining site concrete – sidewalks should also complete in April. Interior of both schools are progressing rapidly every week to prepare for the energizing of both building.

WVSD CP Monthly Report - March 2021

Apple Valley Elementary

The installation of irrigation and placement of topsoil is currently in progress. This process enables the grass hydroseeding of the playfields. Several areas of the building – classrooms in particular – are close to completion, which promotes the starting of the contractors Punch List. This is a very favorable trend, allowing for the low voltage processes to move through the building efficiently. The milestone met this month was the Exterior Siding - Metal Panels - Roofing completion. Multipurpose-Gym are in the completion phase and preparing the Gym Floor Installation. Apple Valley’s construction quality is very evident, and we are excited to show it off to the community soon.


Summitview Elementary

Contractors have found efficiencies allowing for the labor to produce each discipline, accelerating completion of each division. Roofing – Exterior Siding and Metals Panels are expected to be completed in April. Civil, Site and Landscaping moving smoothly and coincides with the installation of the community walking paths. Administration area casework is beginning as well as flooring throughout the building.

Back to news